Five Year Road Plan
Five - Year Local Road Rehabilitation and Maintenance
Priority Schedule 2019 - 2023
|
2019 |
CONSTRUCTION COST ESTIMATE |
|
Front Street Phase 2 – Depot Street to Narrow Gauge Square 1,900 ft. |
$312,961 |
|
Ski Slope Road – Grind and Pave 1,855 ft. |
$36,000 |
|
Webster Road – Pave from Knowlton Corner Road to Wilson Stream Bridge 3,000 ft. |
$54,000 |
|
Overlays – Voter Hill Estates, Prescott Street |
$45,000 |
|
2019 TOTAL |
$447,961 |
|
2020 |
|
|
Perham Street – High Street to New Hope Baptist Church. Construction for partial full-depth reconstruction. Town 50% share of MaineDOT Municipal Partnership Initiative (MPI). |
$265,000 |
|
Lake/Stewart Avenues – Full depth reconstruction. |
$190,000 |
|
Clover Mill Road |
$90,000 |
|
Titcomb Hill Overlay |
$70,000 |
|
2020 TOTAL |
$615,000 |
|
2021 |
|
|
High Street Phase 1 – Perham Street to South Street. Full depth reconstruction |
$300,000 |
|
Titcomb Hill Overlay |
$70,000 |
|
Osborne Road - Pave and chip seal |
$50,000 |
|
Lincoln, Perkins and Quebec Streets - 2,364 total feet |
$120,000 |
|
2021 TOTAL |
$540,000 |
|
2022 |
|
|
High Street Phase 2 – South Street to Rt. 2. Full depth reconstruction. Town 50% share of MaineDOT Municipal Partnership Initiative (MPI). |
$300,000 |
|
Mosher Hill Phase 1 – Full depth reconstruction 7,390 ft. |
$129,000 |
|
2022 TOTAL |
$429,000 |
|
2023 |
|
|
Mosher Hill Phase 2 – Full depth reconstruction 7,390 ft. |
$129,000 |
|
Bailey Hill Reconstruction – Full depth reconstruction 13,728 ft. |
$250,000 |
|
2023 TOTAL |
$379,000 |
|
GRAND TOTAL = $2,410,961 |
|
